  The great pool project began on 27 February 2008...We will maintain a photo chronology of the progress here.

  May 17, 2008 - Filling continues (took 30 hours).

 

  May 16, 2008 - Plaster finished and started filling.

 

  May 8, 2008 - All the electrical and plumbing has been finished, and the deck was finally poured today.

 

  April 12, 2008 - Tiling and coping finished...Apparently the spa is a bit deep!!!

 

 

  April 10, 2008 - Tiling and coping continues...

 

 

  April 9, 2008 - Tiling and coping starts, and I got the fans up...

 

 

  April 3, 2008 - Gunite day...

 

 

  April 3, 2008 - Rebar day...

 

 

  April 2, 2008 - FINALLY HOA Approval Received!!!  Pool dug today...

  03:00 pm

  10:15 am

  09:00 am

  08:00 am

  March 24, 2008 - Replaced patio windows with solid glass...

 

  March 19, 2008 - Patio cover painted and gutters installed...

 

  March 12-13, 2008 - Patio cover "skinned"; pool staked out (delay expected for HOA approvals)...

 

  March 6-7, 2008 - Electrician wires up lights and fans...

 

  March 4, 2008 - Roofing completed...More clips added to framework...

   

  March 4, 2008 - Patio crew get's the lid on...

   

  March 3, 2008 - Patio crew shows up...downpour ensues...nothing accomplished...

  February 28, 2008 - Patio crew puts up exterior header...

   

  February 27, 2008 - Patio crew arrives and sets support posts...

   


This page was last updated on Sunday, May 25, 2008