The great pool project began on 27 February 2008...We will maintain a
photo chronology of the progress here.
May 17, 2008 - Filling continues (took 30
hours).

May 16, 2008 - Plaster finished and
started filling.

May 8, 2008 - All the electrical and
plumbing has been finished, and the deck was finally poured today.

April 12, 2008 - Tiling and coping
finished...Apparently the spa is a bit deep!!!


April 10, 2008 - Tiling and coping
continues...


April 9, 2008 - Tiling and coping starts,
and I got the fans up...


April 3, 2008 - Gunite day...


April 3, 2008 - Rebar day...


April 2, 2008 - FINALLY HOA Approval
Received!!! Pool dug today...
03:00 pm
10:15 am
09:00 am
08:00 am
March 24, 2008 - Replaced patio windows
with solid glass...

March 19, 2008 - Patio cover painted and
gutters installed...

March 12-13, 2008 - Patio cover "skinned";
pool staked out (delay expected for HOA approvals)...

March 6-7, 2008 - Electrician wires up
lights and fans...

March 4, 2008 - Roofing completed...More
clips added to framework...

March 4, 2008 - Patio crew get's the lid
on...

March 3, 2008 - Patio crew shows
up...downpour ensues...nothing accomplished...
February 28, 2008 - Patio crew puts up
exterior header...

February 27, 2008
- Patio crew arrives and sets support posts...
 |